Methodical instructions for secure stability of mine roadways in great depth
Koníček, Petr ; Šňupárek, Richard ; Konečný, Petr ; Ptáček, Jiří ; Kukutsch, Radovan ; Kajzar, Vlastimil ; Waclawik, Petr ; Souček, Kamil ; Staš, Lubomír ; Hortvík, Karel ; Konečný, Pavel
Methodology provides instructions for safe and economic design of roadways for mining and mining design companies in conditions of the Czech part of the Upper Silesian Coal Basin. Methodology covers area of all used roadway support as a steel arch support, rock bolt and cable bolt support as well as methods of grouting for stability and reinforcement of roadways.
Dílčí zpráva V/2012 k projektu Hodnocení kvality HM a geotechnický průzkum pro záměr vybudování podzemního zásobníku plynu Milasín-Bukov - Výčet prací na projektu a zhodnocení dosažených výsledků za čtvrté čtvrtletí roku 2012
Souček, Kamil ; Koníček, Petr ; Vavro, Martin ; Staš, Lubomír ; Ptáček, Jiří ; Vavro, Leona ; Georgiovská, Lucie ; Waclawik, Petr ; Zajícová, Vendula
Dílčí zpráva VI/2013 k projektu Hodnocení kvality HM a geotechnický průzkum pro záměr vybudování podzemního zásobníku plynu Milasín - Bukov - Výčet prací na projektu a zhodnocení dosažených výsledků za čtvrté čtvrtletí roku 2012.
Vypracování jednotného metodického postupu pro dimenzování výztuže důlních chodeb a prorážek
Šňupárek, Richard ; Ptáček, Jiří ; Chura, Jan ; Koníček, Petr ; Konečný, Petr ; Janas, P. ; Polysos, N. ; Nastulczyk, Č. ; Suchánek, J.
Výsledkem řešení projektu je soubor metodických návodů a výpočetních programů pro dimenzování výztuže důlních chodeb a prorážek v podmínkách OKD a.s. Objednatel má k dispozici prostředky pro bezpečné a racionální dimenzování výztuže chodeb v rozhodující většině podmínek OKD a.s.
Project monitoring the stress-strain state of the rock mass during extraction of coal seam 30 (634) within the test run mining methods corridor - a pillar in the OPJ Mine CSM - Sever. Proposal verify the possibility to use anti-shake prognosis and prevention using mining methods corridor - pillar within pilot operation in seam 30 (634) in OPJ Mine CSM - Sever
Waclawik, Petr ; Koníček, Petr ; Ptáček, Jiří ; Šňupárek, Richard ; Kajzar, Vlastimil ; Kukutsch, Radovan ; Vavro, Martin ; Souček, Kamil ; Holečko, J. ; Stoniš, M. ; Suchanek, E. ; Sojka, R. ; Przeczek, A.
On the basis of a contract for No. 850/33/10 and Appendix 1 of this contract , between OKD , as, ČSM and the Institute of Geonics AS CR, v.v.i. we present the following project monitoring stress tension-deformation condition of the rock mass during extraction of coal seam No.30 (634 ) within the test run mining methods corridor - pillar in a protective pillars jam CSM Mine, north location. Monitoring of the stress tension-deformation state of rock mass is a prerequisite for successful verification of a new mining method unapproved hall - pillar and its further use in the Czech part of the Upper Silesian Coal Basin. This mining method is designed on the basis of experiences and practices, which are verified in different natural conditions and depths, and therefore it is necessary for the verification of the conditions of the Czech part of the Upper Silesian Basin on the basis of the proposed geotechnical monitoring. Test operation of the new hall - pillar method will be implemented in the seam No.30 (634 ) in the rock mass included in the category without the risk of shocks.
Progress report on the project VIII/2013 Quality Assessment HM and geotechnical exploration plan for the construction of underground gas storage Milasín-beech - List of works on the project and an evaluation of the results for the third quarter of 2013
Souček, Kamil ; Koníček, Petr ; Vavro, Martin ; Staš, Lubomír ; Ptáček, Jiří ; Vavro, Leona ; Waclawik, Petr ; Georgiovská, Lucie ; Patočka, M.
Based on Contract No. G1042011 with the client fy DIAMO state enterprise Stráž, branch GEAM Lower Rožínka was prepared this interim report, which summarizes the list of works, presents and assesses the findings and results for the period July to September 2013, concerning the evaluation of rock mass quality and geotechnical survey was intended to build an underground gas storage facility.
Progress report on the project VI/2013 Quality Assessment HM and geotechnical exploration plan for the construction of underground gas storage Milasín - Bukov - List of works on the project and an evaluation of the results for the first quarter of 2013
Souček, Kamil ; Koníček, Petr ; Vavro, Martin ; Staš, Lubomír ; Ptáček, Jiří ; Vavro, Leona ; Waclawik, Petr ; Georgiovská, Lucie ; Patočka, M.
Based on Contract No. G1042011 with the client fy DIAMO state enterprise Stráž, branch GEAM Lower Rožínka was prepared this interim report, which summarizes the list of works, presents and assesses the findings and results for the period January-March 2013, concerning the evaluation of rock mass quality and geotechnical survey was intended to build an underground gas storage facility.
Progress report on the project VII/2013 Quality Assessment HM and geotechnical survey for construction of an underground gas storage Milasín - Bukov - List of works on the project and the achieved results for the second quarter of 2013
Souček, Kamil ; Koníček, Petr ; Vavro, Martin ; Staš, Lubomír ; Ptáček, Jiří ; Vavro, Leona ; Waclawik, Petr ; Georgiovská, Lucie ; Patočka, M.
Based on Contract No. G1042011 with the client fy DIAMO state enterprise Stráž, branch GEAM Lower Rožínka was prepared this interim report, which summarizes the list of works, presents and assesses the findings and results for the period April-June 2013, on the evaluation of rock mass quality and geotechnical survey was intended to build an underground gas storage facility.
Hodnocení kvality horského masivu a geotechnický průzkum pro záměr vybudování podzemního zásobníku plynu Milasín - Bukov
Koníček, Petr ; Staš, Lubomír ; Ptáček, Jiří ; Vavro, Leona ; Georgiovská, Lucie ; Stašová, Vendula
Tato souhrnná zpráva hodnotí výsledky provedených prací na projektu Hodnocení kvality HM a geotechnický průzkum pro záměr vybudování podzemního zásobníku plynu Milasín - Bukov. V první části zpravy jsou hodnoceny fyzikálně mechanické a technologické vlastnosti zájmových hornin testovaných na odebraných horninových vzorcích z průzkumného překopu. Druhá oblast se zabývá pracem realizovanými v geotechnické rozrážce. Poslední část zprávy se soustředí na činnost in situ, která se týkala prací pro účely zařazování horninového masivu dle indexových klasifikací RMR aQ, analyzuje a syntetizuje dosažené znalosti a výsledky provedeného průzkumu a udává zatřídění horninového masivu podle indexovaných klasifikací RMR a Q.
Odborné vyjádření k možnosti univerzálního použití metodiky výpočtu stabilních mezichodbových pilířů (ARPMS verze 10) i v jiných slojích v podmínkách české části Hornoslezské uhelné pánve
Šňupárek, Richard ; Koníček, Petr ; Waclawik, Petr ; Ptáček, Jiří ; Staš, Lubomír
Metody stanovení rozměrů stabilních pilířů dobývací metody komora - pilíř udává řada autorů. Jedná se o typické empiricko - analytické inženýrské metody. Ačkoli vesměs vycházejí ze základního statického schematu přenosu vertikální složky zatížení, připadajícíc na plochu pilíře a příslušný podíl plochy okolních komor (chodbic), vlastní výpočtové koeficienty byly stanoveny zpravidla na základě měření a pozorování v konkrétních důlních podmínkách. Použití těchto metod v jiných podmínkách proto má v prvním případě vždy charakter zkušebního provozu, jehož výsledky a získané poznatky teprve umožní další standardní používání této dobývací metody. Tento posudek vedle vlastního zhodnocení projektovaných stabilních pilířů obsahuje návrh monitoringu a sledování, které považujeme za nezbytné pro další používání této metody.

National Repository of Grey Literature : 106 records found   beginprevious76 - 85nextend  jump to record:
See also: similar author names
11 PTÁČEK, Jan
3 Ptáček, J.
7 Ptáček, Jakub
11 Ptáček, Jan
Interested in being notified about new results for this query?
Subscribe to the RSS feed.