National Repository of Grey Literature 47 records found  beginprevious21 - 30nextend  jump to record: Search took 0.02 seconds. 
Evaluation of subsidence caused by application of single-entry room-and-pillar mining method with stable pillars between mined out drifts using the Continuous Miner Technology with full roof bolting. Stage 2 – Development of model for stable pillar dimensioning for single-entry room-and-pillar mining method with Continuous Miner Technology and calculation of surface deformation
Konečný, Petr ; Byczanski, Petr ; Koníček, Petr ; Ptáček, Jiří ; Šňupárek, Richard ; Velička, Vilém ; Zeman, Vladislav
The model solution of stable pillars dimensioning for single-entry room-and-pillar mining method with Continuous Miner Technology is described. Consequently, the parameters of subsidence trough are calculated as an example caused by application of that technology in selected conditions of Ostrava-Karviná Coal Basin.
Evaluation of subsidence caused by application of single-entry room-and-pillar mining method with stable pillars between mined out drifts using the Continuous Miner Technology with full roof bolting. Stage 1 – Development of mathematical model and calculation of expected surface deformation
Konečný, Petr ; Byczanski, Petr ; Koníček, Petr ; Ptáček, Jiří ; Šňupárek, Richard ; Velička, Vilém ; Zeman, Vladislav
Evaluation of subsidence caused by application of single-entry room-and-pillar mining method with stable pillars between mined out drifts using the Continuous Miner Technology with full roof bolting. Stage 1 – Development of mathematical model and calculation of expected surface deformation.
Possibilities of double use of longwall drifts at the Paskov, ČSM and Karviná Collieries
Konečný, Petr ; Ptáček, Jiří ; Šňupárek, Richard ; Velička, Vilém ; Zeman, Vladislav ; Petroš, V. ; Hudeček, V. ; Šancer, J. ; Dvořáček, J. ; Slivka, V.
Analysis of the possibilities of double use of longwall drifts at the Paskov, ČSM and Karviná Colliery with respect to the mining and natural conditions. Conditions for double use longwall drifts, foreign experiences.
Guideline for project planning and support design of longwall drifts intended for double utilization
Konečný, Petr ; Koníček, Petr ; Ptáček, Jiří ; Šňupárek, Richard ; Velička, Vilém ; Zeman, Vladislav
Guideline with principles for selection, realisation and mine support of longwall drifts which are intended for double utilization focused on combined arch and bolt support.
Probabilistic reliability assessment of anchoring reinforcem,ent in mine excavations and underground workings
Janas, P. ; Šňupárek, Richard ; Krejsa, V. ; Krejsa, M.
The paper briefly reviews one of the proposed methods of probabilistic reliability assessment of anchoring reinforcement, usable in mine excavations and underground workings. Application of this concept – software „Kotvení“ was especially developed for this purpose using DDFPM (Direct Determined Fully Probabilistic Method).
Present prospects and tendencies in the field of gateroads securing in coal mines
Šňupárek, Richard
The paper deals with methods of supporting and stabilisation of roadways in coal mines.New investigated and designed methods are connected with double usány of roadways, depth of exploration and environmental requests.Decisive kinds of support include methods of rock mass strenghtening e.g. bolting and grouting.
Ochrana zaměstnanců před důlními otřesy v dlouhých důlních dílech a stanovení opatření při zjištění nebezpečných stavů při vedení a provozu důlních děl s cílem zabránit vzniku otřesu. Projekt č. 44-06. Dílčí zpráva o výsledcích řešení etapy č. 5
Konečný, Petr ; Ptáček, Jiří ; Šňupárek, Richard ; Velička, Vilém ; Zeman, Vladislav ; Bonczek, Č. ; Dvorský, P. ; Holečko, J. ; Koníček, P. ; Przeczek, A. ; Stoniš, M.
Řešení projektu se týká ražeb chodeb a úvodních prorážek pro přípravu nových porubních bloků. Snahou je nalézt nové způsoby preventivních opatření, které by v nich omezily na nejmenší možnou míru riziko otřesů. Kromě toho se v projektu řeší problematika zpřesnění lokace seismických jevů a rovněž zkoumá možnost použití vývrtů po trhací práci pro tlakové zavlažování v rámci protiotřesové prevence.
Ochrana zaměstnanců před důlními otřesy v dlouhých důlních dílech a stanovení opatření při zjištění nebezpečných stavů při vedení a provozu důlních děl s cílem zabránit vzniku otřesu. Projekt č. 44-06. Závěrečná zpráva o výsledcích řešení etapy č. 5
Konečný, Petr ; Ptáček, Jiří ; Šňupárek, Richard ; Velička, Vilém ; Zeman, Vladislav ; Bonczek, Č. ; Holečko, J. ; Koníček, P. ; Przeczek, A. ; Stoniš, M.
Řešení projektu se týká ražeb chodeb a úvodních prorážek pro přípravu nových porubních bloků. Snahou je nalézt nové způsoby preventivních opatření, které by v nich omezily na nejmenší možnou míru riziko otřesů. Kromě toho se v projektu řeší problematika zpřesnění lokace seismických jevů a rovněž zkoumá možnost použití vývrtů po trhací práci pro tlakové zavlažování v rámci protiotřesové prevence.
Study of room and pillar method with stabil pillars between rooms
Konečný, Petr ; Ptáček, Jiří ; Šňupárek, Richard
The study embraces evaluation of the rock mass stability in connection with room and pillar method and a proposal of stability calculation and experimental measures in the condition of CSM mine, evaluation and proposal of the principles rock bolting, analyse of deformations influence of surface and finaly the pilot project of the method aplication.

National Repository of Grey Literature : 47 records found   beginprevious21 - 30nextend  jump to record:
Interested in being notified about new results for this query?
Subscribe to the RSS feed.