National Repository of Grey Literature 2 records found  Search took 0.00 seconds. 
Koks production hall - upper stage of construction
Vaculík, Zdeněk ; Průcha, Aleš (referee) ; Biely, Boris (advisor)
Subject of this work is execution of the superstructure, especially solution of mounted frame included the lining together with the sheathing construction and building roof. The building will serve as assembly and storage hall for the Koks Production company. Reinforced concrete precast frame forms supporting structure. The building is split to two parts, single-storey hall and two-storey administration part. Construction-technological part from complete execution of the building rough superstructure has been selected as a bachelor’s thesis subject. The technological regulation for the assembly of reinforced concrete precast frame has been elaborated. The precast frame is formed by precast elements supplemented by the lining between the columns in the administration part. The solution of following subjects of building construction was taken into consideration too: • solution of suitable site machinery • workers health, safety, and preservation on the site • health protection • test and trial plan for the mounted reinforced concrete skeleton • time schedule and economic analysis for the superstructure • logistics and material storage on the site
Koks production hall - upper stage of construction
Vaculík, Zdeněk ; Průcha, Aleš (referee) ; Biely, Boris (advisor)
Subject of this work is execution of the superstructure, especially solution of mounted frame included the lining together with the sheathing construction and building roof. The building will serve as assembly and storage hall for the Koks Production company. Reinforced concrete precast frame forms supporting structure. The building is split to two parts, single-storey hall and two-storey administration part. Construction-technological part from complete execution of the building rough superstructure has been selected as a bachelor’s thesis subject. The technological regulation for the assembly of reinforced concrete precast frame has been elaborated. The precast frame is formed by precast elements supplemented by the lining between the columns in the administration part. The solution of following subjects of building construction was taken into consideration too: • solution of suitable site machinery • workers health, safety, and preservation on the site • health protection • test and trial plan for the mounted reinforced concrete skeleton • time schedule and economic analysis for the superstructure • logistics and material storage on the site

Interested in being notified about new results for this query?
Subscribe to the RSS feed.