Evaluation of possibilities for connection of wind farm Drahany 45 MW to 110 kV network
Gregr, Tomáš ; Opat, Jaroslav (referee) ; Topolánek, David (advisor)
This Master's thesis is focused on connecting of new power sources into electrical network, particularly, the steady state and allowed voltage variation in network nodes, which occur in steady state before and after connection of a new power source into distribution network, with regard to valid legislation. The new power source in question is the new wind farm Drahany with active power of 45 MW, which should be connected into distribution network 110kV, operated by distribution company E.ON. The aim of this work is to find the most suitable connection point of a wind farm into distribution network, considering transmission capacity of individual electric lines and voltage variations in network nodes, as well as Drahany wind farm's investor's expenses on construction of a connection line to connection point and the distribution network's operator's expenses on modification of the connection point. Also, methods of calculating of electric networks in steady state are described in this paper, particularly, linear calculations, because these are needed for the calculations in E-vlivy program, in which the possible options of Drahany wind farm's connection into network 110 kV, in various places, were modeled. The description of the E-Vlivy program is also included in this paper. The E.ON company's materials form the basis for this Master's thesis, which will later serve as one of the documents needed for Drahany wind farm’s connection point evaluation into distribution network 110 kV.
Evaluation of Possibility of New Source Connection With Regard to Nodal Voltage
Němec, Jan ; Topolánek, David (referee) ; Toman, Petr (advisor)
Connection new source of electrical energy into distribution network is important for existing one for reasons its rating and dimensioning. It is even evaluate, whether possibility connection new source in to network is real and do not endanger continuous running distribution system. This work has shown, what conditions are need realize for connection source into distribution network in view of voltage ratio. Next it must incidence harmonic current and affecting centralized telecontrol signal about reasoning. Against a background examination connection source are administrative acts, which forms basis of successful connection. On basis lets request of connection mostly study of connection working up. This study contains concrete calculation and examination individual factors for connection new source. Next put mind to connection wind power station, because wind power stations are very special source for connection into distribution network. Bigger demands are putting on them and stricter examination of connection to site must be done. Because during time unit (day, week and month) they have various strain diagram. Which makes higher straining of distribution and necessity have reserve of electrical energy for case fail wind power station owing to windless ness. In the end, there is referred to practical examination example of possibility connecting. As this example was chosen examination of wind park to 110 kW network with 32 MVA installed power from view of voltage ratio. Solution process is given by replacement of part of given Picells link and by calculation steady state of node site system with Gauss-Seidels iteration method. After that follows evaluation of voltage change in the site before and after connection of source to the network, which can not be higher than 2%. In this example is this condition satisfied and from a view of voltage ratio there is nothing to obstruct for connection new source to network.
Effective use of 3D Cad systems in the field of process engineering-I
Dítě, Jan ; Dvořák, Radek (referee) ; Pavlas, Martin (advisor)
This work is focused on effecitive use of 3D CAD systems in process and environmetal engineering. The system SolidWorks 2006 is applied. The purpose of this work is to describe creation of basic parts, assemblies and drawings in general way. Special attention is paid on the program unit Routing dedicated for piping system design. The work next describes the importace of reference items required and problems associated with routing subassembly.
Evaluation of Possibility of New Source Connection With Regard to Nodal Voltage
Němec, Jan ; Topolánek, David (referee) ; Toman, Petr (advisor)
Connection new source of electrical energy into distribution network is important for existing one for reasons its rating and dimensioning. It is even evaluate, whether possibility connection new source in to network is real and do not endanger continuous running distribution system. This work has shown, what conditions are need realize for connection source into distribution network in view of voltage ratio. Next it must incidence harmonic current and affecting centralized telecontrol signal about reasoning. Against a background examination connection source are administrative acts, which forms basis of successful connection. On basis lets request of connection mostly study of connection working up. This study contains concrete calculation and examination individual factors for connection new source. Next put mind to connection wind power station, because wind power stations are very special source for connection into distribution network. Bigger demands are putting on them and stricter examination of connection to site must be done. Because during time unit (day, week and month) they have various strain diagram. Which makes higher straining of distribution and necessity have reserve of electrical energy for case fail wind power station owing to windless ness. In the end, there is referred to practical examination example of possibility connecting. As this example was chosen examination of wind park to 110 kW network with 32 MVA installed power from view of voltage ratio. Solution process is given by replacement of part of given Picells link and by calculation steady state of node site system with Gauss-Seidels iteration method. After that follows evaluation of voltage change in the site before and after connection of source to the network, which can not be higher than 2%. In this example is this condition satisfied and from a view of voltage ratio there is nothing to obstruct for connection new source to network.
Evaluation of possibilities for connection of wind farm Drahany 45 MW to 110 kV network
Gregr, Tomáš ; Opat, Jaroslav (referee) ; Topolánek, David (advisor)
This Master's thesis is focused on connecting of new power sources into electrical network, particularly, the steady state and allowed voltage variation in network nodes, which occur in steady state before and after connection of a new power source into distribution network, with regard to valid legislation. The new power source in question is the new wind farm Drahany with active power of 45 MW, which should be connected into distribution network 110kV, operated by distribution company E.ON. The aim of this work is to find the most suitable connection point of a wind farm into distribution network, considering transmission capacity of individual electric lines and voltage variations in network nodes, as well as Drahany wind farm's investor's expenses on construction of a connection line to connection point and the distribution network's operator's expenses on modification of the connection point. Also, methods of calculating of electric networks in steady state are described in this paper, particularly, linear calculations, because these are needed for the calculations in E-vlivy program, in which the possible options of Drahany wind farm's connection into network 110 kV, in various places, were modeled. The description of the E-Vlivy program is also included in this paper. The E.ON company's materials form the basis for this Master's thesis, which will later serve as one of the documents needed for Drahany wind farm’s connection point evaluation into distribution network 110 kV.
Effective use of 3D Cad systems in the field of process engineering-I
Dítě, Jan ; Dvořák, Radek (referee) ; Pavlas, Martin (advisor)
This work is focused on effecitive use of 3D CAD systems in process and environmetal engineering. The system SolidWorks 2006 is applied. The purpose of this work is to describe creation of basic parts, assemblies and drawings in general way. Special attention is paid on the program unit Routing dedicated for piping system design. The work next describes the importace of reference items required and problems associated with routing subassembly.